The project was a full renovation to an existing McDonald’s restaurant in a busy shopping center. There was an expedited timeline of only six weeks to get the entire project completed. The scope included all site demolition of existing parking areas, curbs, sidewalks and even a portion of the building. We also installed 400 LF of a new fire service line which was trenched through a busy parking lot and connected in the main entrance of the shopping center. Additionally, a new sewer main was installed, and all new ADA compliant concrete curbs, sidewalks and parking pads.
Site Demo, Excavation, Water Main, Sewer Main, Concrete Curbs & Sidewalks, Concrete Parking Pads, Asphalt Paving